A video of an innovative wind turbine is presented here
39A, Jerusalem Street. Sofia, BG - 1784, E-mail us Voice / Fax: +3592 8760 431, +3592 8770 481, +3598 9787 2857
Wind Farm Feasibility Study
and Site Layout Design
Starton Engineering JSCo. entering the wind energy market by developing a
portfolio of wind farms. Through a strategic search Starton Engineering JSCo.
identified a series of sites for potential wind farm development in Bulgaria
and several neighbor countries. For increasing of wind power production of
big wind farm is proposed jet blade VAWT s fixed on small towers between the
bigger HAWT turbine. As an example of JET BLADE VAWT
see the
video here.
Starton Engineering JSCo. provides technical and environmental services to progress the priority sites, including a feasibility study for a large site in mountainous and coastal regions. The viability of the site was known to be dependent on the realistic capacity of the wind farm, due to a major cost anticipated in relation to the required Starton Engineering JSCo. provided an initial estimate of potential wind farm capacity at the site, followed by an in-depth study, which determined the feasible number and location of turbines. This was achieved by investigating the technical and environmental constraints experienced at the site and by developing an appropriate wind farm design in response to the specific features of this site and surroundings.
Our team gave consideration to priority issues, including:
• Selection of suitable wind turbine type
• Researching site constraints including protected designations, dwellings
planned land use and infrastructure such as gas pipelines and microwave
links
• Optimisation of energy production based on wind data from a local
Meteorological Station and 3 dimensional wind speed analysis
• Respecting local properties by assessing likely noise levels and currence
of shadow flicker at occupied dwellings
• Understanding visual impact of the proposed project incorporating advice
from our landscape architects regarding sensitive local viewpoints and
landscape-related designations noted from the adopted Local Plan.
The project demonstrated our breadth of understanding of key issues at the
early stage of a wind farm design and development:
• Appreciation that a proposed wind farm size and shape should be based on a
realistically constrained scenario; this pragmatism was particularly
important for actively negotiating the lease agreement for the site, using
our work as a guide to the available income from the site
• Given that visual impact is a crucial planning consideration for wind
farms, we understand the benefit of input and advice from landscape
architects at project inception. Aerotek JSCo incorporated aesthetic
criteria when positioning turbines at the site, including the use of curved
rows of turbines, thus avoiding straight unattractive grids
• The ability to balance technical and environmental concerns when proposing
the feasible capacity of a wind farm site.
• Identification of priority further work including peat probing, vehicle
access
study, consultation with signal operators (Radio communications operators),
and landscape led design study.
Starton Engineering JSCo’s report presented findings and recommendations for the development of a realistically sized wind farm, which would provide high income.
State stimulus for wind power plants in Bulgaria
Power engineering is the fastest progressing branch of the world energetics in the last years, and it is due to a lot of reasons. Most important of them are; rise in the price of energy in general; increasing of the global warming and ecological problems with thermoelectric end atomic power stations, which dominate in the world energetics, increasing of the capacity of wind power generators, and not at the last place – reduction of the prices of the wind power generators on a world scale, toward their level ten years ago. On the background of the described global tendency, the energy policy of our government is completely in unison with the european tendencies for economy and administrative stimulations of energy production from renewable energy sources (RES). The preferential purchase price, for example, of the electricity from RES, in particular from wind, defined from The Commission of energy and water regulation, raised from 6 eurocents per kilowatt-hour in 2003 to nearly 9 eurocents per kilowatt-hour in 2006. Namely the permanent and methodical examination of the euro-energy policy guarantee, that in our state, energy productions from RES will progress ahead of time.
At these profitable preferential legal and economic conditions, the wind climate in more regions in Bulgaria already allows building of effective wind power stations, which are profitable, and at the same time provide not long term of recovery of the investments.
In the colloquial language, and in the meteorology as well, the velocity of the wind is accepted as parallel vectors to each other, square to the terrain, which vectors has changeable at all azimuths direction. But in the reality such wind doesn’t exist; furthermore at the frontier layer of air.
Differential wind energy audit
Generally said, the vector of the wind is not horizontal. Its horizontal
ingredient is this one, which has the energy importance for the operation of
wind generators. But it is part of the wind speed, which has components
along the other two axes of the three-dimensional Cartesian (3-D) space as
well, and these components hinder more or less the work of the wind
turbines.
The results of this measurement are being
analyzed individually as components, and in common.
First goal is sifting out the important energy ingredients of wind from the
other – not useful, which the turbines drug along, and evaluation of the
damages. These damages do not depend only on the not horizontal compounds
but on the amplitude fluctuations of the wind at all directions, called
turbulence, as well.
Designing of wind power plants
At the wind power stations, the primary energy resource (the wind) is
variable at its velocity and its direction. Therefore the designing of wind
power stations always divides into two consecutive phases. The first one is
the wind energy audit, and the second one is the designing itself. Both
phases are even important. First phase is decisive for the choice of
transformation technology of the wind energy into electricity, which has
important meaning for the optimal choice between competitive wind power
generators.
At the second phase are being chosen alternative variants (alternatives) of
wind power generators, on the base of analysis of their technical parameters
of energy and their best correspondence with the specific wind climate
conditions of the audited place.
The project concludes with a technical and economical analysis, investments
and ecological evaluations of the projected alternative versions.
Detailed plan within three steps, of preliminary engineering, is presented below:
Stage 1. WIND ENERGY AUDIT OF TERRAINS
1. Calculation of energy density of the wind currents
1.1. Identification of the terrains
1.2. Profile of the landscape
1.3 . Influences of wind climate over the operation of the wind power
aggregates
1.3.1. Influences of the climate specifics
1.3.2. Influences of the wind dynamic on the work of the wind turbines
1.3.3. Analysis of the results of 3D-measurements
1.3.3.1. Analysis of the turbulence
1.3.3.2. Differential analysis of the wind energy, used for driving wind
aggregate
1.3.3.3. Transformation of the important wind energy into electricity,
according to the parameters of wind aggregates
1.3.3.3.1. Aerodynamic losses of wind energy
1.3.3.3.2. Mechanical and electromagnetic losses
1.4. Diagrams of speed frequencies of the wind at directions for the chosen
places
1.5. Wind-dynamic and analytic modeling
1.5.1. Initial parameters for wind-dynamic modeling
1.5.1.1. Authentic year of measurement
1.5.1.2. Correlating wind-dynamic modeling
1.5.1.4. Correlated wind statistic
1.6. Results of the mean density of the wind energy stream
1.6.1. Calculating method.
1.6.2. Results of the density of the wind energy stream
1.6.3. Results of the density with energy importance, of the wind energy
stream
1.6.4. Expected deviations of the measurements and the results
Stage 2. CHOOSING OF OPTIMAL WIND AGGREGATES FOR THE TERRAINS, ACCORDING TO THE ENERGO-TECHNICAL CRITERIA
2. Determination of the technical
parameters of the wind power generators, in accordance with the results of
wind energy audit
2.1. Fixing the places of foundation of the wind power generators
2.2. Aerodynamic specifics
2.3. Alternatives for the height of the supporting post
2.4. Alternatives for rotors
2.5. Alternatives for transmission and electro generation
2.5.1. Transmissions
2.5.2. Generations and supporting of standard parameters of the electricity
2.5.3. Connecting
2.5.4. Innovative fundamental points
2.5.5. Offer for proper alternatives for the concrete project
2.6. Pessimistic, optimistic and realistic evaluation of the annual
production of electricity for the chosen alternatives of generators
2.6.1. Absolute potential of the annual production of electricity
2.6.1.1. Determination of the average annual operating hours of the wind
aggregates
2.6.1.2. Determination of the actual prevailing wind velocity
2.6.2. Actual annual production of electricity
2.7. Graphic analysis of the capacity and the efficiency of the wind
aggregates
2.8. Parallel between the capacity and the efficiency of the chosen wind
aggregates
Stage 3. TECHNICAL AND ECONOMICAL
ANALYSIS OF THE INVESTMENT EVALUATION OF THE CHOSEN ALTERNATIVE PROJECTS
3. Investment and economical evaluations of the appropriate versions
3.1. Size of investment
3.2. Financial incomings
3.3. Risks and discount percent
3.4. Operational expenses
3.5. Investment cycle
3.6. Period of recovering of the investment
3.7. Net present value of the investment
3.8. Internal norm of profitableness
3.9. Correlation incomes/expenses
3.10. Cost price of the electricity production
3.11. Comparison of the alternatives
3.12. Results of ecological investigation
3.12.1. Ecological evaluation
3.12.2. Ecologically-economical evaluation
3.12.3. Conclusion of the investigation
Final conclusions and recommendations
Not technical criteria of wind power
farm design
In principle, each project has energy-technical and economical part. Here we
will mark formal and economical criteria, which have essential place in the
complete engineering. It is inexpediently for these questions to be
considered in details in one book, because each detailed analysis is
concrete. Such analyses are being made individually for each wind energy
project.
We should mind at firs place, that the choice of over all dimensions and
consequently the capacity of the turbines depends on the terrain and on the
way of using it. There are two formal restrictions, in accordance with
special regulation, where the distances between the turbines and between
them and the urbanized territories, are defined (they exist in project as
well). Distances between 5 to 7 turbine rotors at the direction of the
prevailing wind for the concrete terrain are standardized and 3 to 5
diameters – square to this direction. This is criterion, which provides
relatively good work of a group of turbines, but it doesn’t guarantee
neither their optimal production of electricity, nor their optimal
reliability and durability. For evaluation of these characteristics, it is
necessary to be made configurational project, which is subject of the second
part of this book, whose first edition was published in 2005.
The second formal criterion is the sanitary norm that is determined in a minimum -600 meter from the frontiers of the urbanized territories. Without making detailed comment, we should note that the closeness to transmission line with proper tension and free capacity to export generated electricity from the wind power station also has importance at the engineering stage. If there isn't existing proper electric infrastructure, the time for putting the project into operation will be shortest.
Prices of power generated by wind turbines (feed-in tariff)
Since the beginning of 2007, there are two stage preferential tariff for buying up of the electricity, generated by new wind turbines,
* For wind generators with 2250 (more than
0.257 capacity factor ) and more full effective operational hours annually -
80 euros / MWh
* For wind generators with less than 2250 (below 0.257 capacity factor )
full effective operational hours annually - 90 euros / MWh
The above tariffs are without VAT. As new wind generators are considered turbines, produced later than 01.01.2006. Wind generators, produced before this date, are considered as old, no matter if they are exploited or not.
From the table we can see that the differences are quite big and they will have significant influence over the investment indexes, as well as on the size of the needed opening stock.
Even without making such analyses, one can see that it is economically profitable the turbines to work less than 2250 hours, in comparison with the case, when they would have worked a little bit more than this hour limit This refers to new machines. If they are not big, their transport and their montage will be not expensive and in the long run it could be turned out that they are economically more effective over terrains, where the wind conditions are more unfavorabl. But If the machines are cheap (second hand) and proper aggregates are being mounted on windy places the, than their economical efficiency could be better in comparison with the new machines, no matter that the buying up tariff is considerably lower.
This brief analysis gives us the possibility to understand, that universal proper choice of aggregates doesn’t exist. They can be small or big; new or old; horizontally-axial or vertically-axial; individually working, or a few in a big group – wind park; or in few smaller groups etc. All reciprocally excluding alternatives mentioned here, can be combined in different ways. But providing for the height of the generators over the terrain and their initial expenses, the problem appears with ambiguitive solution.
The tariffs above will be subject of increase, because according to the Energy Law, they may not be lower than 70% of the end price of electricity for the home consumers.
Designing of innovative wind turbines
In large numbers one can see the propeller wind turbines. They work optimally, when the horizontal component of the complex vector of the wind is parallel to their rotor shaft. That’s why these turbines are being frequently called horizontally axial HAWT. The basic disadvantage of HAWT is that their rotor always revolves not only around its horizontal shaft, but it also moves at 360 angular degrees at the azimuth. This necessity complicates the structure of the entire turbine, and make it more expensive, furthermore if considering that the rotor is posed high above the terrain and the mechanical forces from the pressure of the wind as well as the bending moments they create, are considerable, which impose the rotors to be mounted on solid and massive supporting towers and respectively fundaments. All these problems can be avoided, if the wind turbines are constructed in such way, that is not necessary the revolving of the rotors around two mutually perpendicular axles, but only around one – the axle of their rotor shaft. Such machines are constructed, most frequently, with vertical rotor shafts and their blades turn around vertical axle. They are being called vertically axial machines or VAWT.VAWT are relatively simple in their structure and have significant advantage, that their center of gravity is low, close to the terrain, in contrast to the center of gravity of HAWT. For that reason the forces and the bending moments over their supporting construction, are vastly reduced. After all said till now, naturally appears the question why the horizontal axial propeller machines are much more distributed in practice than the vertical axial turbines.
The answer of the question, in brief, comes
from the fact that the blades of propeller machines are loaded only from one
side – the side of the wind pressure direction, and that’s because the rotor
always revolves so, that the wind is parallel to its shaft. From mechanical,
dynamical and kinematical point of view, the unilateral load over the blades
is more advantageous, and therefore the rotors of HAWT are much more lighter
and can rotate with higher revolutions, because the centrifugal forces in
them are smaller. For each revolution of the vertical axial machine, its
blades pass through two positions, in which they are loaded bilaterally
consecutively. Such librating load over the blades for each revolution is a
reason for them to be made robust, respectively heavy, the centrifugal
forces are being got big and the rotors, as a whole, revolve unstable,
particularly at high revolutions. And the energy effectiveness at
transformation of the kinetic energy of the wind into useful work, when
revolving the shaft of the turbine, strongly increases with the rise of the
revolutions. Therefore, even if in principle, two prime kinds of turbines
have a nearly even theoretical effectiveness, the limitation of the rise of
revolutions of the vertical axial turbines, make their real energy
effectiveness lower.
However, in contradiction from the horizontally axial turbines, which are unstable in not horizontal and turbulent wind flows, the vertically axial turbines are slightly sensitive in not horizontal and turbulent wind flows; furthermore they are considerably more noiseless. The last two characteristics make them applicable also for populated places, where the wind flows are turbulent, and where the noise during their operation time is unallowable.
That’s why our efforts are concentrated on designing of innovative vertically axial turbines, which are discussed in these pages. JET augmented Savonius vertical axis turbine have the best performance in the comparison of any drag turbine in both flow wind and water - more see here. In the case of Darrius and Darrius-like vertical rotors the jet blade is more efficient than the any airfoil blade rotors in very broad turbulent wind speed spectrum - more see here..
And the optimal engineering and constructing of the blades, rotors, transmissions and generators of the vertically axial machines, we make on the base of detailed study of the not laminar character of the wind flows. This study we carry out with equipment for 3-dimensional measurement of the characteristics of air currents, which we briefly call differential 3D wind audit.
Cybernetic system for wind farm control - Patent pending
Vertical and horizontal wind shears, yaw misalignment and/or turbulence act together to produce asymmetric loading across a wind turbine rotor. The resultant load produces bending moments in the blades that are reacted through the blades, hub and low-speed shaft. The amount of blade’s deflection is measured using one or more sensors placed on the turbine tower. The output signals from the sensors are used to determine the magnitude of the resultant rotor load. This information is used to effect the blade pitch change needed to reduce the load and thereby reduce fatigue and loading on various turbine components.
Full title of the invention is: “Method and control system for blades load of the turbines and turbulence minimization in a wind farm based on blades deflection and turbulence of turbine wake flow” according to our pending patent. The mentioned method is applicable after low cost and very simple wind turbine upgrade.
Autor and inventor: George Tonchev, Ph.D.
For patent publications - see here .
For further information
e-mail me